Data Centers

Frequently Asked Questions (FAQs)

What is a Data Center?

Data centers are facilities that consist of one or more buildings used primarily for the storage, management, processing, and transmission of large amounts of digital data and which houses computing infrastructure, such as, computers, network equipment, systems, servers, appliances, and other associated components related to digital data operations.

The current Moratorium on Data Centers will provide the County with sufficient time to develop policies, performance standards, and updated zoning regulations which will be the foundation that guides future proposals. 

Data Processing Facilities/Centers are mentioned in the current Zoning Ordinance but not expressly defined. Data Processing Facilities/Centers are currently principal permitted uses in the Planned Industrial District (PI), the Airport District (AP), the Office Research and Industry District (ORI), the Office Research and Technology District (ORT), and the Education, Research and Technology District (ERT). 

Current County land use and zoning continues to protect rural areas such as the Priority Preservation Areas and the Rural Legacy Area. 

Click here to view the Zoning Ordinance | https://www.washco-md.net/wp-content/uploads/county-attny-Zoning-Ord.pdf.

Click here to view the Zoning Map | https://arcg.is/q9XOu1.

Staff have researched best practices and below is a summary of topics that will be provided to the Planning Commission for review and potential incorporation into County Zoning and Land Use Ordinances:

  • Energy plan that utilizes alternate, self generating power, and returns power to the grid to prevent shifting costs onto everyday ratepayers. This should include a potential prohibition of natural gas turbines. Back up energy sources should consider the prohibition of lithium-ion batteries.
  • Water plan that utilizes water recycling, incorporates drought planning and utilizes geothermal or alternative cooling technologies.
  • Noise study that evaluates pre and post construction noise (dBA and dBC). Limit noise to a maximum of 50 dBA at the property line and reduction of dBC tonal / narrow band noise to background noise levels. 
  • Require installation of noise barriers such as trees, berms, etc.
  • When reviewing setbacks from residential homes that are present now or that may be constructed in the future, a minimum setback of 1,000 ft should considered.
  • Study of air quality and environmental impacts.
  • Limit development to areas zoned Planned Industrial (PI) AND by Special Exception only. The Special Exception designation means that the developer will be required to submit a request to the Board of Zoning Appeals (BZA) before a permit may be issued; and, the BZA will review the application, conduct a Public Hearing and obtain public input before making a decision. 
  • Development of an appropriate Excise Tax or Impact Fee.
If you have a comment, question or additional consideration please contact us:

Email us at:  [email protected]

You may also send comments or concerns via regular mail to:

Department of Planning and Zoning

747 Northern Avenue

Hagerstown, MD 21742

Yes, the County does have data centers of varying size. There are no pending data center applications and no new applications are being taken during the moratorium.

The County’s ability to regulate all aspects of a data center is limited by federal and state laws. In Maryland, local governments cannot regulate air pollution, energy generation and transmission, or water quality. The U.S. Congress and the Maryland General Assembly can pass laws affecting these issues. The U.S. Environmental Protection Agency and Federal Energy Regulatory Commission have an oversight and enforcement role at the federal level. The Maryland Department of the Environment and the Maryland Public Service Commission have similar responsibilities at the state level. Learn more about the state’s processes

Email us at:  [email protected]

You may also send comments or concerns via regular mail to:

Department of Planning and Zoning

747 Northern Avenue

Hagerstown, MD 21742

Over time data centers have changed in size and purpose. Washington County has typically seen rooms or floors of a building used to support that facility’s needs. Mid-Sized data backup centers or processing centers also exist in the County.

1970’s – Rooms or floors of a building

1980’s – Small Buildings

1990’s – Mid-Sized Buildings

2000’s – Large Warehouses

2010’s – Massive Space, millions of square feet

Yes, the County has existing data processing facilities of varying size excluding Hyperscale.

Micro = Compact, modular units deployed in dense urban areas or remote locations. Example: A server to support a local business on site.

Edge = Smaller, distributed sites near end users to reduce latency for real-time applications. Example: A cellular towers support infrastructure directly adjacent to it or a local fiber provider’s facility.

Enterprise = On-premise facilities serving a single organizations internal IT needs. Example: A facility used as a dedicated backup location for data.

Hyperscale = Massive facilities (100,000+ sq ft) operated by cloud giants like AWS, Google, and Microsoft.

Section §4-416 of the MD Annotated Code of Local Government specifically states that “if an area is annexed to a municipality that has planning and zoning authority at the time of annexation, the municipality shall have exclusive jurisdiction over planning, subdivision control, and zoning in the area annexed.” This means that the Washington County Data Center Moratorium is applicable only to the unincorporated areas of Washington County. The incorporated areas of Washington County include the City of Hagerstown, and the Towns of Clear Spring, Hancock, Boonsboro, Keedysville, Smithsburg, Williamsport, Funkstown, and Sharpsburg; and, zoning regulations in those incorporated areas are not governed by the Board of County Commissioners. As a result, each of the municipalities may still consider data center development without any input or approvals by the Commissioners except as provided in Section §4-416 b as it relates to the development of annexed land where the land uses are substantially different than the authorized use previously classified by the County at the time of annexation.

No, there are no pending data center applications and no plans will be accepted during the moratorium.

When plans are proposed their approval would be handled by the Planning Commission. The Department of Planning and Zoning continues to provide an interactive map of all pending applications and previously approved plans and plats in the Development Tracker web application https://arcg.is/1zO9iP0

The Department of Planning and Zoning provides an interactive map of all pending applications and previously approved plans and plats in the Development Tracker web application https://arcg.is/1zO9iP0

Email us at:  [email protected]

You may also send comments or concerns via regular mail to:

Department of Planning and Zoning

747 Northern Avenue

Hagerstown, MD 21742

Workshop Materials and Presentations

Upcoming

AGENDA (Tentative)

WASHINGTON COUNTY PLANNING COMMISSION WORKSHOP

100 W Washington Street, Room 2000

January 21, 2027, 1:00 to 3:00 PM

 CALL TO ORDER AND ROLL CALL

WORKSHOP TOPIC:  Data Center Information Gathering and Discussion

  1. Guest Speakers: A brief presentation to address the topic as it relates to their area of expertise and to answer questions from Staff and Planning Commission members.
    • Mr. Joe Kroboth, Deputy County Administrator, Loudoun County, VA (1:00 pm – TBD)
  2. Planning Commission follow-up and discussion with Staff (2:30-3:00 pm)

ADJOURNMENT

Previous Workshops

AGENDA

WASHINGTON COUNTY PLANNING COMMISSION WORKSHOP

100 W Washington Street, Room 2000

November 13, 2026, 1:00 to 3:00 PM

 CALL TO ORDER AND ROLL CALL

WORKSHOP TOPIC:  Data Center Information Gathering and Discussion

  1. Guest Speakers: A brief presentation to address the topic as it relates to their area of expertise and to answer questions from Staff and Planning Commission members.
    • Ms. Kelly Schulz, Maryland Tech Council (1:00 to 1:45 pm)
    • Ms. Vanessa Akins and Ms. Heather Urwiller, Prince George’s County Planning Department (1:45 to 2:30 pm)
  2. Planning Commission follow-up and discussion with Staff (2:30-3:00 pm)

ADJOURNMENT

AGENDA

WASHINGTON COUNTY PLANNING COMMISSION WORKSHOP

100 W Washington Street, Room 2000

October 8, 2026, 2:00 to 4:00 PM

 CALL TO ORDER AND ROLL CALL

WORKSHOP TOPIC:  Data Center Information Gathering and Discussion

  1. Guest Speakers: Allotted 30 minutes for a brief presentation to address the topic as it relates to their area of expertise and to answer questions from Staff and Planning Commission members.
  • David Kline, First Energy (2:00 to 2:30 pm)
  • Nancy Hausrath, City of Hagerstown Utilities Department (2:30 to 3:00 pm)
  • Quentin Clapper, Planning Director, Franklin County, PA (3:00 to 3:30 pm)
  1. Planning Commission follow-up and discussion with Staff (3:30 to 4:00 pm)

ADJOURNMENT

Current Timeline of Data Centers in Washington County, Maryland

Timeline Key: The Department of Planning and Zoning (Dept) is responsible for establishing and implementing short and long term land use planning goals that help maintain a balanced and diversified land base for our community.  The Planning Commission (PC) contains seven citizens appointed by the Board of County Commissioners (BOCC).  The PC is charged with reviewing and approving subdivision plats, forest conservation plans, site plans, and development plans. The Commission also acts in an advisory capacity to the BOCC on items such as rezoning requests, ordinance text amendments, and adoption of other land use regulations and programs. The five-member Washington County Board of Commissioners (BOCC) is the county’s elected governing body.

Moratorium Goes Into Effect

The BOCC approved a temporary, twelve (12) month moratorium on the acceptance, processing, reviewing and approval of applications, plans, or requests for data centers within Washington County. 

The moratorium will provide the County with sufficient time to develop policies, performance standards, and zoning regulations which will be the foundation that guides future proposals. 

Click to view the meeting video.

Click to view the Ordinance ORD-2026-12

Staff Review

Staff across a variety of County Departments including the Department of Planning and Zoning begin additional research on data centers with a focus on best practices for these centers.

Planning Commission Workshops Begin

The Planning Commission conducts workshops to evaluate and research impacts of data center development on environmental resources, utilities, local infrastructure and land use compatibility. 

Planning Commission Discussion and Proposed Local Regulations

After conclusion of workshops, the PC will formulate directions for Department of Planning and Zoning staff to begin any drafts of ordinance changes or creation of standards.

Evaluate any Proposed State Legislation

When the State legislative session begins, the County will review any proposed legislation to ensure any draft updates to local ordinances or standards are compatible and consistent.

Draft Ordinances and Standards

Staff will formulate a draft of any local zoning amendments or standards using the input of the Planning Commission and staff research.

Public Input Meeting(s) with PC

The PC will hold public information meetings to obtain public comment on drafts. These meetings will be announced on the County website and in the local newspaper when a date and time is chosen.

BOCC Public Hearing

The BOCC will hold a public hearing to review the draft recommended by the Planning Commission and to obtain additional citizen comment. This hearing will be announced on the County website and in the local newspaper when a date and time is chosen.

Moratorium Ends

The temporary moratorium ends.

Tuesday, June 30, 2026
July - September 2026
October 8, 2026
December 2026 - January 2027
January 2027 - February 2027
February - March 2027
March - April 2027
May - June 2027
June 30, 2027

Ask Questions or Provide Comments

Do you have comments or questions regarding Data Centers?

Email us at: [email protected]

You can also send comments via regular mail to:

Department of Planning and Zoning

747 Northern Avenue

Hagerstown, MD 21742

Additional Resources

These additional resources are provided to citizens for information purposes. These resources are mentioned in presentations by speakers at workshops or additional research materials reviewed by the Planning Commission and/or staff.

External Link Note: These links are being provided as a convenience and for informational purposes only; they do not constitute an endorsement or an approval by Washington County, MD of any of the products, services or opinions of the corporation or organization or individual. Washington County, MD bears no responsibility for the accuracy, legality or content of the external site or for that of subsequent links. Contact the external site for answers to questions regarding its content.