Flood Recovery Updates

Washington County, Maryland

South County Update - 8/7/2018

Chestnut Grove Road – project will open August 31st instead of mid-August.

Sandy Hook Road– notice to proceed from Asturian Group. There will be a road closure in a few weeks to Sandy Hook Road

Garrett’s Mill Road – Building Systems – design build project of 1.25 million dollars. Project was advertised and competitively bid. 75% FEMA, 25% local for budget. 225 consecutive day project.

Back Road – looking at moving forward in rebuilding the road, a new culvert, and stream restoration. 75% FEMA reimbursement project. Preliminary plans will happen this fall, work will be bid out during the winter with work beginning in the spring.

Pipes are installed on Back Road and Limekiln Road with pavement installation happening. Things have happened slower due to excessive amount of rain.

Posted in floodupdates and tagged , .